The lag between hydrogen and renewables investment announcements and materials demand

Type
Kaltec Voices
Published
24 November 2026
Prepared by
Minkyung Choi
Role
Research Analyst

Materials orders for hydrogen and renewables projects do not wait for the target year in the announcement; they arrive earlier, changing shape at equipment contracts, construction start and commissioning. Reading announcements, auction results, equipment orders, construction starts and commissioning in turn, with a different probability of moving to the next stage, shows which volumes are needed in which quarter.

Background

In late April 2020, a plan was announced to build a liquid hydrogen plant of 13,000 tonnes a year in Ulsan. Construction was to start in the first quarter of the next year, with completion in 2022 (Newsis, 2020). The groundbreaking came a quarter late, on June 21, 2021, and the target stated that day was operation in May 2023 (Digital Times, 2021). Commercial production then slipped again, from December 2023 to the second half of 2024, and a January 2026 report had the plant still in commissioning (Dealsite, 2026). For every project I write the announcement date, the construction start and each revised operating target side by side on one line of a tracker.

On that line, the date that matters to people who buy and supply materials is not the operating target at the end. Long-lead equipment such as compressors and stacks is contracted soon after the final investment decision, anti-corrosion coating goes on within months of construction start, and the first fill of lubricants and cooling water goes in before commissioning. Materials orders do not wait for the target year; they come earlier, changing shape at each stage. Delay does not only push orders back, either; it also creates new ones. So when I turn an investment announcement into demand, I first count which stage each project is at now and how likely it is to move to the next, before the announced size.

The volume that shrinks from announcement to construction

The list of announced hydrogen projects worldwide is shrinking year by year. In its 2025 review, the International Energy Agency said that 9% of low-emission hydrogen production projects due by 2030 had reached a final investment decision. The output announced projects could deliver by 2030 fell from 49 million tonnes a year to 37 million tonnes in one year (IEA, 2025). The 2026 review cut that again to 27 million tonnes. It also judged that, without investment decisions by early 2027, 22 million tonnes' worth could lose a realistic chance of operating within 2030. In 2025 alone, global electrolyser capacity doubled to over 4 GW, and nearly three quarters of the newly installed capacity was in China (IEA, 2026).

Domestic power generation figures have the same shape. In the first clean hydrogen power auction in 2024, six plants bid 6,172 GWh a year, and one won, with 750 GWh a year. Commercial operation was set for around 2028 (MOTIE, 2024). The 2025 auction was canceled on October 17 after it was announced, and the notice reissued on October 30, 2026, cut the clean hydrogen volume to 500 GWh a year and dropped coal co-firing plants from eligibility (Lawtimes, 2026).

On target numbers alone, refuelling stations look on track. Seventy-five were built in 2025, meeting the cumulative target of 450, and the 2026 target is 500 or more in total (Segye, 2026). Following a single operator tells a different story. According to a report citing National Assembly Budget Office data, one station operator had yet to complete 8 of its 19 sites, and completion of the Siheung Bangsan station slipped 50 months, from April 2023 to June 2027. The same report said the station construction budget falls 36.9% in the 2027 government budget proposal (SBS, 2026).

That is how small the share left after each stage is. The IEA's 9% means fewer than one in ten announced projects reached an investment decision, and the volume awarded in the 2024 auction was about 12% of the volume bid. So I give each stage a different weight. A project with only an announcement and an MOU goes on the list with zero volume. Once an auction result or a permit comes out, I put construction start in a range of a few quarters, and only projects with a confirmed construction start get volume in a set quarter. To turn one project into volume, I use equipment-level factors such as the first fill of one compressor or coating per tonne of steel structure.

Orders that change at each stage from investment decision to operation

Once the final investment decision is made, long-lead equipment such as compressors, electrolyser stacks and heat exchangers is contracted first. What gets fixed at this point is spec more than volume, and the first fill fluids are usually also chosen then from the equipment maker's approved list. Whether seals and lubricants can stand up to high-pressure hydrogen is a matter for separate testing; what I put into the count is the quarter that order arrives.

From construction start to mechanical completion, single-use construction materials go in. Steel frames and foundations get anti-corrosion coating, and high-pressure piping needs degreasing and cleaning before joining. Hydrogen piping avoids chemical residue for purity, so it is dried and sealed with nitrogen after the hydrostatic test, and corrosion inhibitors go into the cooling water and general utility piping.

From commissioning on, orders become maintenance consumables that come back every year. These include compressor oil changes, top-ups and treatment chemicals for the cooling system, valve grease, and touch-up coating on coastal sites.

When actual orders arrive does not match the target year. In the hydrogen projects I have watched, the first enquiries bunched in the quarter construction start was confirmed and the one after, rather than in the year of the operating target. Seen from one place across many industries, each project's orders are small, but the orders of projects that broke ground in the same quarter pile up at once.

Delay pushes some orders back and creates others

When construction start slips, construction materials slip with it. But equipment contracted before construction comes out on the fabrication schedule and can arrive before the site is ready. Then, while compressors and heat exchangers with nowhere to go sit in storage for months, new storage preservation orders arise for rust preventive oil, vapor corrosion inhibitors and nitrogen blanketing. This order does not end with one delivery. The preservation applied at shipment assumes a set storage period, so the longer storage runs, the more often rust preventive oil is reapplied, vapor corrosion inhibitors are replaced and nitrogen pressure is checked and topped up, all the way to construction start. So for a delayed project, alongside the count that pushes construction materials back, a separate count for storage preservation arises for each month storage continues. If commissioning drags on, routine maintenance volume starts that much later. For a project whose operating target slipped several times, like the liquid hydrogen plant above, operating-stage volume planned around the target year has nowhere to go in the meantime.

Auction terms are a clue to reading this lag. Under the 2026 notice, a clean hydrogen winner that fails to spend at least 30% of total investment within 18 months of the contract can have the contract canceled or terminated. For general hydrogen winners it is at least 50% within 12 months. Clean hydrogen projects must start generating by 2030 after a three-year preparation period, and preferred bidders are announced on June 18, 2027 (Lawtimes, 2026). If contracts are signed in summer 2027, the 30% deadline falls between late 2028 and early 2029. Spending 30% of total investment requires major equipment contracts and construction start before then. As there is no award yet, these projects still carry zero volume in my table. But I set the slots in advance: if they win, construction start goes within 2028 and the first fill between 2029 and 2030.

On the same day, a fixed-price contract auction for about 2,200 MW of offshore wind was also announced (Lawtimes, 2026). In offshore wind, heavy-duty corrosion coating on the substructures goes in at fabrication and grout at installation, while gearbox oil for geared turbines and transformer insulating oil go in as first fill before commissioning. The stages from award through equipment orders and construction start to commissioning are followed the same way as for hydrogen.

Putting it to work

A company tied to hydrogen or renewables projects through equipment, parts or operations can use the following signals as thresholds in its materials plan.

At announcements and MOUs, check whether the equipment type is stated next to the project size and target year.

At auction results and permits, note the preferred bidder announcement and the permit deadline. The 2026 general hydrogen auction requires winners to obtain a generation business permit by June 30, 2027 (Lawtimes, 2026). The permit deadline becomes the front edge of the construction start range.

Equipment orders show up in listed companies' new facility investment filings or equipment makers' order disclosures. At this point, check which items are on the maker's approved list, and for imported items start counting lead time from here. If equipment delivery is fixed before construction has started, mark here where storage preservation will be needed.

For construction start, treat the groundbreaking date only as a starting point and confirm it again through the construction start filing or a disclosure. Once confirmed, align construction material volumes and delivery to that quarter.

For a refuelling station, the threshold for commissioning is the completion inspection by the Korea Gas Safety Corporation. From here, count maintenance volume by change interval rather than by year.

Seen in this order, the questions for choosing supply become concrete too. Supply that plans volume around the target year has nothing on hand when the first order of the construction quarter comes, and if the project slips, that share sits in the warehouse. You can ask the supply side which stage they see your project at now, and from which signal they start counting lead time for imported items. The answer tells you whether the first volume will be ready in the construction quarter.

Conclusion

The road from investment announcement to order narrows at every stage, and the shape of the order changes at each stage crossed. Delay does not push the whole flow back at once; it pushes construction materials back while creating new orders, such as storage preservation for equipment that arrived early.

Once awards are made, materials orders for clean hydrogen projects that must start generating by 2030 will come before 2030, from 2028, when the investment deadline falls.

The next date in my table is June 18, 2027.

Sources

  • Dealsite. (2026). Hyosung Heavy Industries' delayed hydrogen value chain: liquid hydrogen stations stall, Seungju Lee, January 9, 2026. https://dealsite.co.kr/articles/154721
  • Digital Times. (2021). Hyosung and Linde break ground on liquid hydrogen plant, join hands for carbon neutrality with hydrogen technology, Wisu Kim, June 21, 2021. https://www.dt.co.kr/article/11393675
  • International Energy Agency [IEA]. (2025). Global Hydrogen Review 2025: Executive summary, September 2025. https://www.iea.org/reports/global-hydrogen-review-2025/executive-summary
  • International Energy Agency [IEA]. (2026). Global Hydrogen Review 2026: Executive summary, 2026. https://www.iea.org/reports/global-hydrogen-review-2026/executive-summary
  • Lawtimes. (2026). Second-half 2026 offshore wind and hydrogen power competitive auction notices and implications, Law Times, Mihyun Park and Shinyoung Yoon, November 19, 2026. https://www.lawtimes.co.kr/news/articleView.html?idxno=229717
  • Ministry of Trade, Industry and Energy [MOTIE]. (2024). First step toward clean hydrogen power, Ministry of Trade, Industry and Energy press release, December 3, 2024. https://www.motir.go.kr/kor/article/ATCL3f49a5a8c/169876/view
  • Newsis. (2020). Hyosung to build the world's largest liquid hydrogen plant, roundup, April 28, 2020. https://www.newsis.com/view/NISX20200428_0001009008
  • SBS Biz [SBS]. (2026). More hydrogen cars, but what about stations? Completion drags on, Juyeon Seo, October 26, 2026, citing the National Assembly Budget Office, "2026 Public Institutions: Status and Issues." https://biz.sbs.co.kr/amp/article/20000342154
  • Segye. (2026). 7,820 hydrogen cars to be supplied in 2026 with 576.2 billion won in state funds, Segye Ilbo, Wooseok Choi, January 5, 2026. https://www.segye.com/newsView/20260104508460

Product and site consultation

Leave your company, site and the product groups in use. Our engineer will get in touch to go through your site conditions and concerns. Materials, equipment, operating conditions and downstream steps show what should change and what can stay. If nothing needs to change, we will say so.

Contact us
After you contact us
  1. 01
    Site setup

    We confirm process conditions and needs first.

  2. 02
    Spec design

    We set the product spec and selection criteria.

  3. 03
    Comparison

    We compare matching candidates and propose.

  4. 04
    Tailored supply

    We supply on time and manage the stock.

  5. 05
    Site check

    We visit, check conditions of use and record.

  6. 06
    Use management

    We track use and change cycles to catch issues.

  7. 07
    Regular analysis

    We analyze the records and send a yearly report.