BlogKaltec Voices
Why safety stock for imports should be set with the supplier
- Type
- Kaltec Voices
- Published
- 24 November 2026
- Prepared by
- Subum Jang
- Role
- Logistics Staff
The safety stock formula for imports needs both the consumption rate the customer knows and the lead time variation by leg that the supplier holds, so neither side's numbers can fill it alone. Only with dates recorded at every leg, from shipment preparation to domestic transport, can the variation to cover with stock be told apart from the variation to cut by order timing or routing.
Background
I once drew the last twelve receipts of a solvent-free rust preventive wax we import from Japan as a bar chart. Each receipt got one bar, stacked in colors for shipment preparation, waiting for loading, the voyage, transshipment, customs clearance and domestic transport. Shipment preparation, which took up more than half of each bar, was almost the same length except on receipts that ran into holidays, and the voyage of a few days ran through as an even thin band. Only the customs segment was different. Ten times it passed thinly in a day or two, but twice it shot up to nearly ten days and pushed the end of the bar out by more than a week.
The customer plant that uses that wax had set its safety stock as the quoted lead time plus a few weeks of margin, and that number had stayed the same for years. Before asking how many weeks the margin should be, there were other questions. Which leg's variation is that margin meant to cover, and who is measuring and recording that variation? Lead time variation is not in the quote. It is scattered across the dates on the shipping and customs documents the supplier receives. Safety stock for imports is set only when the customer, who knows the consumption rate, and the supplier, who holds the dates by leg, put their numbers into one formula together.
Stock shaken by customs, a leg that is short on average
People say goods from a nearby country like Japan need less safety stock because the voyage is short. The voyage is short, that much is true. But the length of a lead time and its variation do different jobs. If you know it takes 7 weeks, you order 7 weeks ahead, so length is mostly covered by order timing, and safety stock only takes the swing in consumption during those 7 weeks. Variation goes straight into safety stock, because safety stock is what covers the receipts where 7 weeks becomes 8 or 9. So even the longest leg, shipment preparation, does not add much safety stock if its dates are even, and a short customs leg that is uneven does.
Turn the customs segment of the chart into numbers and the mean is about three days, with a standard deviation of about three days too. By standard deviation alone, customs is just a leg that swings a little more than the others. Yet draw a normal distribution with that mean and standard deviation, and a receipt taking nearly ten days comes up once or twice in a hundred. In fact it was twice in twelve. A leg that rarely but sharply spikes looks small when measured by standard deviation, and the days the warehouse runs low always come from those spikes.
Customs spikes like this because of things that pick out particular receipts, such as being selected for inspection or having to supplement documents. Customs may inspect goods to be imported (MOLEG, n.d.), and the importer cannot know in advance which receipt will be selected. For chemical products, a few days can also be added when customs asks again about tariff classification or chemical substance confirmation documents have to be redone. The two long receipts for that wax had different causes from each other.
The wax is solvent-free and not classified as a flammable liquid on its safety data sheet, so there was no waiting for dangerous goods loading procedures, and that is why the wait for loading was fairly even. On the same route, a solvent-based rust preventive oil would have made a differently shaped bar. Until you draw the bars for each item, you end up guessing which leg causes the swing.
Two terms of the formula, held by customer and supplier
This wax is ordered when stock reaches the reorder point. For items like this, safety stock is a factor set to the service level multiplied by the square root of the sum of two terms (Silver et al., 2017). The demand term is the mean lead time times the square of the weekly consumption variation. The lead time term is the square of the mean weekly consumption times the square of the lead time variation. Say the line uses 8 pails a week on average, swinging by about 2 pails week to week, and the lead time averages 7 weeks with a standard deviation of about five days across all legs, including holiday receipts and customs. The demand term is 28 and the lead time term is close to 33. Multiply by the factor for a 95% level and safety stock comes to about 13 pails, a little over a week and a half.
Many purchasing systems take one number in the lead time field and a separate gut-feel number in the safety stock field. When the quote's 7 weeks goes into the lead time field, lead time variation in the formula becomes 0, and only 28 is left under the square root. At the same service level, safety stock shrinks to about two thirds of what it should be. Even if the quoted 7 weeks is right as an average, a lead time written as one number erases variation from the formula. The margin that customer plant had added also differed from this value, and on the two receipts where customs ran long, it had used almost all of that margin just before the goods arrived.
The numbers for the two terms are in different hands. The customer, who has the line's records, knows weekly consumption and its variation. The order and receipt dates in the customer's ledger can also give the variation of the total lead time. But for an item imported five or six times a year, the ledger holds five or six rows a year, and with that few rows a single ten-day receipt swings the standard deviation hard. Those rows do not show which leg grew either. Pool the volume of several customers bringing in the same wax on the same route, and receipts in the same period multiply several times over, each with leg dates attached, so you can see where the time grew. I build leg statistics from receipts pooled that way. On its own the customer struggles to fill the lead time term reliably, and on its own the supplier cannot fill the demand term or the service level.
Responses you can only choose by leg
Splitting by leg also shows that not every swing should be covered with safety stock. The Japanese manufacturer's shipment preparation ran long on receipts that fell over the late April to early May holidays, Obon in mid August, and the year-end and New Year period. Variation tied to the calendar can be known in advance. You only need to order earlier for those receipts, with no reason to keep safety stock high all year. Measure variation only on the receipts left after taking these out, or the formula inflates. Take out receipts that fall over Seollal and Chuseok as well, but since customs and domestic transport tend to grow together then, set how many days to order early by adding both legs.
For an item that swings at transshipment or at consolidated cargo cutoffs, look at routing and shipping method before stock. If waiting for the next vessel happens often, moving to a loading port with a direct service, even at somewhat higher freight, can cost less than stacking two more weeks of safety stock. Wax piled up loses remaining shelf life in the meantime and ties up warehouse space and money.
The calculation above bundled all legs into one standard deviation, but a leg that rarely and sharply spikes, like customs, is better left out of the formula. Put only the evenly swinging legs into the formula by standard deviation, and cover the spiking leg by adding to safety stock the consumption for the days by which the longest past receipt exceeded the mean. Preparing documents before loading does reduce the long receipts, but it cannot remove inspection selection.
Putting it to work
Setting it together does not end with one meeting. You have to divide who supplies which numbers, and when both go into one formula to be recalibrated.
The numbers the supplier brings are dates by leg. For each receipt, write nine dates on one row: order confirmation, shipment preparation complete, loading, arrival and departure at the transshipment port, arrival at the destination port, entry into the bonded area, customs release and receipt at the customer. The bonded entry date keeps days spent waiting to unload from being counted as customs. Add the mean, standard deviation and longest days for each leg over the last twelve receipts, and mark calendar-tied receipts separately. Also pass on anything that will change variation ahead, such as news of a change in the manufacturer's holiday schedule, loading port or transshipment port.
The customer brings the consumption rate. That means weekly consumption and its variation on the lines using that wax, the weeks in next quarter's production plan when consumption will change, and how often a stockout is acceptable for each item. The last number is set by the production and quality staff, who know whether the line stops when the wax runs out or whether domestic stock can fill the gap within a few days.
The cycle for recalibrating together is once a quarter plus a few events. Each quarter, put both numbers into the formula to work out safety stock again, and note the lowest stock level just before each receipt alongside. If stock before receipt never fell below safety stock over several quarters, it was set too high, and if it often did, too low. When the loading or transshipment port changes, customs requirements change, or a line's consumption changes a lot, do not wait for the quarter. The customer for this wax and I put the two tables side by side in the first week of each quarter.
Conclusion
The safety stock formula for imports takes numbers from two sides, customer and supplier. Consumption rate sits on the customer's line and variation by leg sits in the dates on the supplier's documents, so if one side fills the other's field with a single number, the formula looks right but does not cover the late receipts. Loading ports, transshipment routes and customs requirements change a little every year, and each time the leg where variation gathers changes too. The quoted lead time cannot keep up with that change. What will last in import trade is supply that pools many receipts on the same route, measures dates by leg, and puts those numbers into one formula with the customer's consumption rate every quarter.
The lead time variation field covers late receipts only when it is filled with the leg dates the supplier holds.
Sources
- Ministry of Government Legislation [MOLEG]. (n.d.). Customs Act Article 246, Inspection of goods. Korean Law Information Center. Accessed November 2026.
- Silver, E. A., Pyke, D. F., & Thomas, D. J. (2017). Inventory and production management in supply chains (4th ed.). CRC Press.