What lowest-price awards cost in maintenance chemicals for power plant and railway tenders

Type
Kaltec Voices
Published
24 November 2026
Prepared by
Unjung Kim
Role
Operations Staff

Turbine control fluid and lubricator grease that match the same specification numbers still part ways in acid number after mixing with the fluid in the tank and in pump pressure on the first cold-snap morning, and that is where the maintenance cost of a lowest-price award comes from. A tender that announces mixing test results with the tank fluid, winter test-section records and delivery records on the same equipment as evaluation items in the specification round weighs that cost before the award and answers objections on fairness and audit with documents.

Background

Last year two of the maintenance chemical tenders we bid on chose their winner in different ways. A coal-fired plant's top-up of turbine control fluid went to the lowest bidder first checked on delivery record and credit rating, and awarded to the first one that passed. A regional headquarters of a railway operator buying rail lubricator grease first reviewed records of a full winter on a test section and low-temperature test results, and only those that passed competed on price. What I heard from the two sites the next year also differed. The plant's chemistry engineer said the top-up fluid came from a different maker than the fluid in the tank, so they sent out a separate mixing test and changed the purification media earlier than planned. The track engineer at the railway's facilities office said they got through the first cold snap without a single lubricator call-out.

Both winning bids were under the estimated price, and both specifications were thorough. The difference was whether the evaluation looked at the months after delivery. Maintenance chemicals are usually added to a fluid that is already circulating or fed into a device already installed. So the cost a lowest-price award leaves shows up in readings taken after mixing with the fluid in the tank and in the maintenance log of the first winter. For a public tender to see those months in advance, it has to announce mixing test results and delivery records on the same equipment as evaluation items. Only when those records exist as documents does the evaluation stand up to questions of fairness, budget and audit.

What a top-up fluid that meets the spec meets in the tank

The electro-hydraulic control system of a large steam turbine usually runs on a fire-resistant triaryl phosphate ester fluid, which plant staff call EH fluid. It is a complex mixture made from substituted phenols such as xylenols and tertiary-butylphenol, and it is prone to hydrolysis (ISO, 2017). Water that gets in breaks the fluid down into acids, and the higher the acid number climbs, the faster the fluid degrades. There is also a warning that fluid with too high an acid number cannot be recovered by common purification methods (Brown & Hobbs, 2019). So plants circulate the fluid through purification media such as ion exchange resin and measure acid number, water and volume resistivity on a set schedule. One turbine maker's 2012 limits keep water below 1,000 ppm and resistivity above 10 GΩ·cm. When resistivity falls, currents generated by the flowing fluid erode the metering edges of the servo valves (Brown & Hobbs, 2019).

A public tender can rarely name a product, so the specification lists numbers a new fluid must meet and accepts products equal or better. There is a separate international standard for new fluid that the maintenance guidance points to (ISO, 2017), and most products bid meet its numbers. But a top-up goes into fluid that has been circulating for years, and two products that meet the same standard can differ in their blend of feedstock phenols. That is why the maintenance guidance gives incoming testing of new fluid and topping up their own sections (ISO, 2017). When a top-up arrives from a different maker, the chemistry engineer checks air release, foam and acid number again on a mixed sample of the two fluids before adding it, and measures acid number and resistivity more often than usual for some months afterwards.

For that plant's tender I multiplied the drum price gap between first and second place by a year's top-up volume and set it against the extra mixing test fees the plant paid and the cost of changing the purification media early. The second figure was larger.

The test lubricator grease faces on the first cold-snap morning

A lubricator beside the rail on a curve pushes grease up each time a wheel passes and spreads it on the inside face of the rail, reducing wear and squeal between wheel flange and rail gauge face. If the grease stiffens in winter and cannot pass the hose and the applicator bar, the gauge face takes trains dry. If it thins and spreads onto the railhead, friction drops on the surface the wheels roll on.

The European standard for flange lubricants replaced its predecessor in 2022 and requires control of production lots and a data sheet on top of product specification and verification. It also sets annex tests for water washout, steel corrosion, behavior at high temperature and slumping. Lubricator grease for trackside units must have its penetration at minus 25 degrees measured in type testing, while a pass limit applies only to vehicle-mounted units (CEN, 2022). It is a standard built to check, for the whole supply period, that a product verified once comes out the same lot after lot. Specifications in Korean tenders tend to list room-temperature numbers such as dropping point and penetration first, and often leave out low-temperature numbers such as the grease's flow pressure at the local midwinter temperature. The cost of that gap comes due at the first cold snap: night call-outs to clear blocked nozzles, faster gauge face wear on dry curves, and rail replacement brought forward.

What qualification reviews count as a record, and what they do not

Contracts of public corporations such as the power generation companies and Korea Railroad Corporation follow the rules on contract affairs for public corporations and quasi-governmental institutions, and anything those rules do not cover follows the national contract law (MOLEG, n.d.-a). The qualification review common in goods purchasing checks contract performance capability starting from the lowest bidder under the estimated price and picks the winner from there (MOLEG, n.d.-b). What the review counts shows in its scoring table. Take the criteria for purchasing products reserved for competition among SMEs: delivery record scores the amount or quantity of equal or similar goods delivered in the last five years against the size of this purchase. For purchases of 1 billion won or more, the 100 points split into 5 for delivery record, 10 for technical capability, 30 for financial standing and 55 for bid price; below the notified threshold, there is no delivery record score, only 30 for financial standing and 70 for price. Either way, a bidder needs 88 points or more to win (MSS, 2026). This record counts how much was sold, not how the goods did on that equipment. In smaller purchases it is not counted at all.

The enforcement decree of the national contract law offers another path. It provides for two-stage competition, where a specification or technical round comes first and only those found qualified enter a price round; even then, the lowest price among the qualified wins (MOLEG, n.d.-b). In construction, citing dumping bids and poor workmanship, lowest-price awards were removed in 2016 for public works of 30 billion won or more, replaced by a comprehensive evaluation system that weighs construction records and quality ratings alongside price (Seoul Shinmun, 2015). A specification round for maintenance chemicals can take three kinds of records: test results when mixed with the fluid now in the equipment, delivery records on the same kind of equipment, and a history of consistent quality lot after lot. For EH fluid, the first means results from an accredited lab on air release, foam, acid number and resistivity after the buyer mixes the bid product at a set ratio into in-service fluid drawn from its own tank. Lubricator grease has no fluid to mix with, so a record of a full winter on a test section with that model of lubricator fills the place.

Putting it to work

When maintenance staff put forward a specification round, the same three objections tend to come back at the contract review. All three can be answered with records kept as documents.

"Won't this favor only incumbents with records?" That is the fairness objection. It will, if the delivery record must come from that plant or that line. Widen the requirement to the same kind of equipment anywhere, so that for phosphate ester control systems a delivery to any plant counts. A bidder without records can still submit mixing test results. The buyer gives every bidder the same amount of tank sample and writes pass limits for acid number rise and air release time as numbers in the notice. A running turbine cannot be topped up as a trial, so the plant side finishes verification in the lab; a railway opens a test section before the notice.

"If a pricier bidder wins, what about the budget?" That is the budget objection. Price competition remains in two-stage competition, because those who pass the specification round compete again on the lowest price. The approval request shows how far the award price might rise, along with the number of mixing tests and analyses ordered around top-ups in recent years and the cost of changing purification media early. At one plant, I was told, the specification round passed once these numbers went in alongside it.

"Won't the audit ask why the lowest bid was set aside?" That is the audit objection. An audit usually checks whether the qualification requirements narrowed competition unfairly, whether the criteria were announced in advance, whether the same criteria applied to every bidder, and whether the basis for each decision was kept in writing. Technical scores given on an evaluator's impressions are weak on these questions. Scores based on accredited test results, delivery certificates issued by buyers and lot quality records carry a supporting document for each decision, and at the audit those documents can simply be laid open.

When notices change this way, the papers bidders prepare change too. The ones that pass the specification round have delivery records of topping up tanks that held another maker's fluid, with mixing test results, and have written down which lubricator ran at what pressure in midwinter and had the buyer confirm it. The papers we submitted in the railway's specification round were also records of pump pressure and coverage taken on midwinter mornings for each test-section lubricator, with the track engineer's confirmation attached.

Conclusion

The cost a lowest-price award leaves in maintenance chemicals comes from numbers the specification does not list: the numbers after mixing with the fluid in today's tank, and the numbers on a local midwinter morning. Announce those numbers as evaluation items in the specification round and back them with delivery records, and that cost goes on the scoring sheet before the award. A plant that keeps a specification listing only new-fluid numbers pays that cost from its maintenance budget for months after another maker's fluid enters the tank.

The evaluation items written in this year's notice get scored on the first cold-snap morning in December.

Sources

  • Brown, K. J., & Hobbs, M. (2019). Understanding EHC fluid condition monitoring. STLE 2019 Annual Meeting, Power Generation II, Session 8C. https://www.stle.org/images/pdf/STLE_ORG/AM2019%20Presentations/Power%20Generation/STLE2019_Power%20Generation%20II_Session%208C_K.%20Brown_Understanding%20EHC%20Fluid%20Condition%20Monitoring.pdf
  • European Committee for Standardization [CEN]. (2022). EN 15427-2-1:2022 Railway applications, Wheel/rail friction management, Part 2-1: Properties and characteristics, Flange lubricants. Supersedes EN 16028:2012. CEN.
  • International Organization for Standardization [ISO]. (2017). ISO 11365:2017 Petroleum and related products, Requirements and guidance for the maintenance of triaryl phosphate ester turbine control fluids. ISO. The edition before the 2025 second edition.
  • Ministry of Government Legislation [MOLEG]. (n.d.-a). Rules on Contract Affairs of Public Corporations and Quasi-governmental Institutions, Article 2, Paragraph 5, Application of other laws. National Law Information Center. Accessed November 2026.
  • Ministry of Government Legislation [MOLEG]. (n.d.-b). Enforcement Decree of the Act on Contracts to Which the State Is a Party, Article 18, Two-stage competitive bidding, and Article 42, Selection of the successful bidder in competitive bidding charged to the national treasury. National Law Information Center. Accessed November 2026.
  • Ministry of SMEs and Startups [MSS]. (2026). Detailed standards for contract performance capability review in purchasing goods among products reserved for competition among SMEs, Ministry of SMEs and Startups Notice No. 2026-80, effective October 1, 2026. National Law Information Center.
  • Seoul Shinmun. (2015). Lowest-price awards abolished for public works of 30 billion won or more. Seoul Shinmun, December 30, 2015. https://m.go.seoul.co.kr/news/2015/12/30/20151230011028

Product and site consultation

Leave your company, site and the product groups in use. Our engineer will get in touch to go through your site conditions and concerns. Materials, equipment, operating conditions and downstream steps show what should change and what can stay. If nothing needs to change, we will say so.

Contact us
After you contact us
  1. 01
    Site setup

    We confirm process conditions and needs first.

  2. 02
    Spec design

    We set the product spec and selection criteria.

  3. 03
    Comparison

    We compare matching candidates and propose.

  4. 04
    Tailored supply

    We supply on time and manage the stock.

  5. 05
    Site check

    We visit, check conditions of use and record.

  6. 06
    Use management

    We track use and change cycles to catch issues.

  7. 07
    Regular analysis

    We analyze the records and send a yearly report.