Why application records get the next plant running sooner

Type
Kaltec Voices
Published
24 November 2026
Prepared by
Jonghwan Moon
Role
Technical Staff

A battery cell plant's dry room puts humidity, static and contamination conditions on roll press grease and seals, and the equipment maker's recommended list does not cover all of them. When a supplier brings the lines changed at the previous plant, with the reason for each, into the new plant's design review, fewer first choices need retesting at commissioning and target yield comes sooner.

Background

In the first week of commissioning at a new battery cell plant, I stood in a cleanroom suit at a roll press inside the dry room. In my hand was the recommended grease list the equipment maker had handed over, and the grease in the roll bearing row was one the same company's previous plant had already replaced in its first year of operation. The previous plant knew what it had gone through with that grease and what it had switched to. Had that reached the maker at design review, this line would not have become homework for the first week of commissioning.

The maker's recommended list is the answer for running the machine at its rated performance. In a cell plant, the conditions the dry room and the cell impose come on top of that. The answers to those conditions, above all for first choices such as the grease, seals and cleaners picked at the start, usually exist only in the previous plant's records. The previous plant's application records cut the number of first choices a new plant has to retest in commissioning and early production, and bring the day it reaches target yield that much closer.

Dry room conditions the maker's list cannot fully cover

Even one roll press has many lubrication points: the roll bearings, the hydraulic cylinders that load the rolls and their seals, the mechanism that sets the roll gap, and the bearings on the shafts that unwind and rewind the electrode. A common layout puts the hydraulic unit outside the dry room and runs only the piping in, so the hydraulic oil meets outside air while the cylinders move inside the dry room. The thin oil film that passes the rod seal comes into the dry room, so seal material and wipers belong on the lubrication line too. Each point meets different air and temperature, so one line on one list cannot give every answer.

The dew point standard also differs by process step. Cell assembly areas usually sit between minus 35 and minus 45 degrees Celsius, and demanding areas such as electrolyte filling for next-generation cells can go below minus 60 degrees (Leventcov, 2024). The electrode area where the roll press stands is usually kept less dry than that. Even so, low humidity changes the shape of lubrication work. Products that contain water, such as water-based cleaners, cannot come in, and even one can of grease brings an airlock, unpacking and waiting time. The worker who opens a point to top it up also gives off moisture, so the longer the job, the higher the room's dew point climbs.

When the air is dry, static builds up easily too. ESD Association data show a person working at a bench at 6,000 volts at 10 to 25% relative humidity and 100 volts at 65 to 90% (ESDA, 2020). Dry room air is far drier than that, and charge also builds on the rolls and electrode sheets turning inside it. Grease droplets that get past a seal, or wear particles from a bearing, may then be drawn toward the rolls and electrodes rather than falling to the floor.

Metal contamination harms the cell directly. Burrs on electrode edges or metal spatter can pierce the separator and cause an internal short (Liu et al., 2021). Some plants remove lubricants containing copper or zinc from their standard to cut metal contamination. On a roll press with heated rolls, heat has to be weighed as well. The hotter grease gets, the more base oil it releases, and released oil that passes the seal can reach the electrode. So when choosing grease for the heated roll side, oil separation and evaporation loss at high temperature go into the criteria.

Small first choices that stretch a new plant's schedule

A new cell plant loses time not only in the big equipment but also in small first choices. Everyone watches the coaters and winders, but the grease, seals and cleaners go in as the maker's list says and get a second look only when trouble starts. A white paper on plant ramp-up reports that scrap rates of 15 to 30% are common in cell production for the first few years and stay around 10% even after five years. In a 40 GWh a year plant, one percentage point of scrap costs about 30,000 euros a day, and each day production starts late wipes out 1.1 million euros of profit (Bockey & Heimes, 2024). The same white paper did not treat production delays of more than seven months and initial scrap above 30% as a startup problem alone. It found the same numbers at established makers that copy Asian plant designs almost unchanged into Europe. Even experienced makers struggle to carry knowledge from existing plants into new ones. Drawings can move, but what was changed on top of them, and why, does not move unless someone writes it down.

The makers' recommended lists I have seen were mostly filled with general-purpose products. Because the same model of roll press also sells to film and metal foil lines in other industries, the maker lists products any plant can source and the machine warranty can stand on. For the maker, that is the right choice. But it is not a list written with that plant's cells and dry room in mind.

Fixing one wrong first choice inside a dry room costs more than outside. You open the point, bring the new grease in through the entry procedure, wait for the raised dew point to come back down, and confirm there are no traces on the electrode surface. Holding that dew point is not cheap to begin with. In one analysis of pilot-scale cell production, the dry room used 29% of all energy (Liu et al., 2021). Finding the cause takes time too. Defects from contamination do not show at the roll press right away, and often surface in the self-discharge test that sorts out cells whose voltage drops during aging. From there, the trail back to the roll press grease is long.

How the previous plant's records sort first choices

What the previous plant's records give a new plant is not a list of right answers but a sorting of first choices. Hold the new plant's lubrication points against those records and they fall into three groups. Points already solved at the previous plant carry over as they are. Points where conditions changed, even on the same equipment, get a second look. Equipment the previous plant never had is tested from scratch. Only the last two groups need testing at commissioning, and the thicker the records, the larger the first group.

This sorting comes only from records that put on one line the dew point standard of the area where the machine stands, the roll and bearing temperatures, what was used first, what replaced it and why. If the reason for a change on the heated roll bearing line was oil separation, for example, you decide by the new plant's roll temperature. If it was a banned ingredient, you carry it over as is. Lines that carry over are settled at design review, and only lines to recheck use commissioning time. A line missing its reason makes the new plant run the same test once more.

Even plants of the same company differ in conditions. A move to a more moisture-sensitive material, such as a cathode with higher nickel content, lowers the dew point standard, and a plant that raised its roll temperature needs a different answer for bearing grease.

How harmful a given contaminant is to that cell, the cell maker's process and quality engineers know better than I do. I do not make that call for them. I pull the lubrication facts they need out of the records and lay them out.

Yet lines like these often break between one plant and the next. The previous plant's maintenance staff often do not move to the new plant, and the reasons for changes slip out easily at the handover, when the maintenance team takes over the top-ups the maker's setup crew did during commissioning. Then only product names reach the new plant's design review. What holds those lines across plants, reasons included, is the supplier who made the changes at the previous plant and wrote them down.

Putting it to work

The records are used at four points in a new plant's schedule.

Design review. Before the maker's recommended list comes out, the new plant's equipment lead sits down with the supplier's contact who brought the previous plant's records and pulls up the lubrication lines for equipment in the dry room areas. They match the previous plant's lubrication point chart against the new equipment's, line by line, and write banned ingredients, water-containing products and heated roll bearing temperatures into the purchase specification. A line carries over only if someone who can explain each change is at the table, and the commissioning homework shrinks by that much.

Equipment move-in. Decide which surface rust preventives to wipe off and which to replace before the equipment enters the dry room. Build the time the entry procedure takes into the first top-up plan, and size the spare grease kept inside the dry room to match.

Commissioning. Test only the last two groups sorted earlier. Record roll temperature, bearing temperature and electrode surface inspection results under the same date, and if a problem turns up weeks later in the self-discharge test, the trail back to the roll press is shorter.

First month of production. Start recording the first top-ups and first changes in the same format as the previous plant. This is when the maintenance team takes over top-ups from the setup crew, and if conditions and reasons drop out here, the break at the previous plant repeats itself. The new plant's first-month records become the material to bring to the next plant's design review.

Conclusion

On lines using more moisture-sensitive materials such as high-nickel cathodes, I expect dry rooms to get drier and contamination standards to get stricter. As long as the same roll press sells into many industries, the maker's recommended list will follow that change a step behind. The one who writes the change down first is the supplier who records the previous plant's tests with their reasons and brings them to the next plant's design review.

An answer the previous plant wrote down with its reason does not go back on the commissioning list.

Sources

  • Bockey, G., & Heimes, H. (2024). Mastering ramp-up of battery production [White paper]. Fraunhofer Research Institution for Battery Cell Production FFB; PEM der RWTH Aachen University.
  • EOS/ESD Association, Inc. [ESDA]. (2020). Fundamentals of electrostatic discharge, part one: An introduction to ESD. https://www.esda.org/esd-fundamentals/part-1-an-introduction-to-esd/
  • Leventcov, A. (2024, April 26). Clean room atmosphere requirements for battery production. AFRY. https://afry.com/en/insight/clean-room-atmosphere-requirements-battery-production
  • Liu, Y., Zhang, R., Wang, J., & Wang, Y. (2021). Current and future lithium-ion battery manufacturing. iScience, 24(4), 102332.

Product and site consultation

Leave your company, site and the product groups in use. Our engineer will get in touch to go through your site conditions and concerns. Materials, equipment, operating conditions and downstream steps show what should change and what can stay. If nothing needs to change, we will say so.

Contact us
After you contact us
  1. 01
    Site setup

    We confirm process conditions and needs first.

  2. 02
    Spec design

    We set the product spec and selection criteria.

  3. 03
    Comparison

    We compare matching candidates and propose.

  4. 04
    Tailored supply

    We supply on time and manage the stock.

  5. 05
    Site check

    We visit, check conditions of use and record.

  6. 06
    Use management

    We track use and change cycles to catch issues.

  7. 07
    Regular analysis

    We analyze the records and send a yearly report.