BlogKaltec Voices
Why corrosion control in shipbuilding and offshore is a planning problem
- Type
- Kaltec Voices
- Published
- 24 November 2026
- Prepared by
- Jaemin Seo
- Role
- Technical Staff
How many years a shipyard's block coating lasts is largely settled by conditions before the paint can is opened: salt and dust left on the steel, the gap between steel temperature and dew point, and the order of painting from block to erection. Laying the rainy season, high summer and winter over the block schedule and changing surface preparation and painting order by season leaves fewer areas for touch-up after erection.
Background
One dawn in the rainy season, I opened the door of a block painting cell and found a thin film of moisture on the steel of a double-bottom block that had been blasted the afternoon before. A gloved finger drawn across it left a wet streak on the gray surface. Before switching on the spray pump, the painting foreman asked whether the cell dehumidifier had run all night, then stuck a magnetic surface thermometer on the plate. Once the dew dried, the spots showing a red tinge were blasted again, and the block's first coat slipped to the afternoon.
When I start talking corrosion with shipbuilding customers, the conversation usually begins with paint. Which paint lasts longer, whether switching products cuts down on blistering. But no paint can fix that dawn moisture. The International Maritime Organization's coating standard for ballast tanks aims for a coating that stays in good condition for 15 years (IMO, 2006). A coat applied over that dawn moisture traps the water beneath it and misses the target within a few years, in blisters and lifting. The same standard notes that faults in surface preparation and painting are very hard to correct later (IMO, 2006). As I see it, corrosion control in a shipyard is a planning problem. What state the surface is brought to, and in which season and order it is painted, has to be settled on the block schedule before the paint is chosen.
What stays below a grade given by eye
Steel is blasted once on arrival and given a shop primer. After it is built into blocks, the surface damaged by welding and handling is prepared again. This IMO coating performance standard, usually called PSPC, has that second preparation blast damaged shop primer and welds to Sa 2½, with a surface profile of 30 to 75 μm (IMO, 2006). Sa 2½ is a cleanliness grade judged by eye against photo references, so what the eye cannot see is measured separately. Dust is lifted with tape and checked for quantity and size, and dust of size class 3 to 5 must be at quantity rating 1 or lower. Water-soluble salt is measured by the conductivity of purified water washed over the steel inside a patch stuck to it. The limit is 50 mg/m² as sodium chloride, measured at least at one spot on each block before the first coat (IMO, 2006).
Salt settles long before painting. While primed steel is stacked in a seaside stockyard, and while finished blocks stand in the yard waiting their turn in the cell, the sea wind carries salt in. A coat laid over remaining salt draws in water and swells into blisters over a few years of ballast going in and out. If a reading is over the limit, the surface is washed with fresh water, dried and measured again, and if rust shows on the washed surface, blasting starts over. If the day for washing, drying and remeasuring is not on the block schedule, measuring becomes something people want to skip.
Steel warms later than the air
PSPC rules out painting when relative humidity is above 85% or the steel is not at least 3°C above the dew point, and sets the same condition for the first blasting of steel (IMO, 2006). Run the numbers for a rainy-season morning: air at 25°C and 80% relative humidity has a dew point of about 21.3°C, so the steel must be above 24.3°C. The humidity is within the limit, but if thick plate that cooled overnight is still at 22°C, that surface cannot be painted yet. Thick plate holds a lot of heat and warms well behind the air as the morning gets warmer. That hour, with warm humid air and only the steel cold, is when condensation comes most easily. The standard has steel temperature, humidity and dew point measured and recorded at block stage, during painting and curing, and those records pass through the daily painting log into the coating technical file that stays with the ship (IMO, 2006).
Before a move, a paperhanger checks how dry the wall is before unrolling a single sample, and if the moving date is fixed, counts back from the day the wall will be dry. In block painting too, waiting for the steel to dry and warm means the wait has to be in the schedule beforehand. If the gap between blasting and first coat runs long, the surface rusts again and loses its grade, so which block gets the cell dehumidifier and heater, and when, is tied into one plan with the blasting order.
Areas left at block stage become the ship's weakest
Pre-erection painting at block stage is the best chance to paint with humidity and temperature controlled in the cell. The butt welds where blocks will join are left bare then, and painted after erection and welding, from scaffolding in the dock. PSPC calls for those joints to be prepared with power tools to St 3 or better, and to Sa 2½ where possible (IMO, 2006). Joints inside ballast tanks sit in tight spaces reached through manholes, so dehumidifier hoses and ventilation ducts have to be pulled in, and the standard keeps ventilation going during painting and for some time after (IMO, 2006). These bands, painted in places poorer than the cell, are where rust tends to show first on the ship.
Weld an outfitting support to the far side of a block already painted, and the heat crosses the plate and burns the coat. This back-side weld damage also ends up as touch-up. So raising the pre-erection painting rate shortens dock time, but on blocks where pre-outfitting could not keep pace, burnt spots and touch-up grow and the weak areas can actually multiply.
Pre-erection painting in the cell also takes days, as many as there are coats. Edges are ground to a radius of 2 mm or more, or ground three times, and two stripe coats go on edges and weld lines by brush or roller. A stripe coat is a coat too, so each one is cured as the maker advises before the next goes on. That is why the painting work instructions must include the maker's overcoating intervals (IMO, 2006). The lower the temperature, the longer the minimum interval, so the same block needs more days per coat in winter. In areas like the shell, where only the primer goes on at block stage and the next coat in dock, the gap easily stretches to weeks. Past the maximum interval, the coat has to be abraded and washed of the salt and dust that settled in the meantime before the next coat will hold.
Putting it to work
Spread out the block schedule and lay the rainy season, high summer and winter over it. Mark which season each block's blasting date, first-coat date and erection date fall in, and even under the same coating spec, what needs adjusting looks different by season. On this season-layered schedule, here is what I fix together with the production planner.
Blocks in rainy-season weeks are sequenced so blasting and first coat happen within the same day, and they get the cell dehumidifiers first. Morning painting starts not by the clock but when the steel is more than 3 degrees above the dew point. A day for rewashing and remeasuring salt goes into that week in advance.
In high summer, the steel of shell and deck blocks in the sun gets too hot to touch. Solvent flashes off so fast that spray droplets dry before they reach the plate, giving dry spray, and the pot life of mixed paint shortens. Such blocks are moved to the low-sun hours of morning and evening, and the steel temperature range for application from the paint data sheet is written next to the schedule.
For blocks whose erection bunches up in winter, I choose paint whose overcoating interval and low-temperature curing conditions fit that month's steel temperature, and book heaters and insulating covers for the dock joint painting to match the erection dates. If epoxy cured on a cold, damp day grows amine blush, a greasy, waxy film, on its surface, it is washed off before the next coat.
Which block enters the dock when, and which week gets crowded, is set by the production planner's schedule. When that schedule changes, the season-layered schedule has to be fixed the same day. The paint maker's technical staff, the owner's inspector and the coating inspector are already in the cell every day. If they take charge of the day's blocks, I take charge of carrying the day's records into the schedule for the next blocks. The weeks I spend most time in the cell are the week the rainy season starts and the week of the first cold snap. In those weeks I read the daily painting log's steel temperatures, dew points and salt readings with the foreman and fix the order of the next blocks on the schedule.
Conclusion
Blocks whose schedule includes a day to wash off salt and a morning to wait out the dew point leave fewer areas to repaint from scaffolding after erection. There are more of those blocks when a season-layered schedule sits on the table at the paint selection meeting, and when a supplier comes to the cell every week the season turns to read the records together and fix the order of the next blocks.
More of the yards I visit these days are speeding up block turnover to cut the time between blasting and first coat, and between primer and the next coat. In those yards, the floor on turnover is set by the minimum overcoating interval in the data sheet and that season's steel temperature, and that floor is highest for winter blocks.
A coat's 15 years start before the paint can is opened, on a block schedule with the seasons written in.
Sources
- International Maritime Organization [IMO]. (2006). Performance standard for protective coatings for dedicated seawater ballast tanks in all types of ships and double-side skin spaces of bulk carriers (Resolution MSC.215(82)). IMO. https://wwwcdn.imo.org/localresources/en/KnowledgeCentre/IndexofIMOResolutions/MSCResolutions/MSC.215(82).pdf